How does a 13% projected power increase justify a 33% 50% increase
in fracked methane delivered by a third new pipeline?
And why isn’t FPL doing more with solar power in the Sunshine State?
Updated 12 August 2014: Fixed 50% increase, which was so absurdly high that I didn’t believe it when I first wrote this. Yet 3/2 is a 50% increase.
FPL’s 10-Year Site Plan web page says:
FPL submitted its 10-Year Power Plant Site Plan 2014-2023 to the Florida Public Service Commission in April 2014.
The document includes on page 37
FPL’s own Schedule 2.1 History and Forecast of Energy Consumption
And Number of Customers by Customer Class (Projected),
which shows 55,739 GWh for 2014 and 62,870 GWh projected for 2023.
That’s an increase of 13% over a decade.
How does that (very aggressive) forecasted increase
justify a natural gas increase of 33% 50% by adding a third pipeline?
(And by the way, those numbers are significantly less than
the numbers in FPL’s 2011 plan of
54,364 GWh in 2011 and a projection of 63,575 GWh in 2020 for an increase of 17%.
The current plan projects only 60,791 GWh for 2020.)
The U.S. Environmental Protection Agency (EPA) was smart to ask FERC to get Sabal Trail Transmission and FPL to provide evidence for need for their huge yard-wide 100-foot-right of way fracked methane pipeline. Because FPL’s own numbers don’t support such a need.
Even if that forecasted new electricity need is correct,
why not solar and wind, as
EPA also asked FERC?
FPL sure could improve its solar generation.
According to Table 1.A.1: Capacity Resource by Unit Type (as of December 31, 2010 December 31, 2013),
FPL generates 23,687 megawatts (MW) of power, including:
- 3,453 nuclear (Turkey Point and St. Lucie)
- 254 coal SJRPP, Jacksonville, FL
- 643 coal Plant Scherer, Monroe County, GA (that’s right, FPL operates a coal unit dirtying the air in the geographical center of Georgia)
- the vast majority gas or oil or some mix
- 0 MW Wind, unchanged from the 2011 plan
- 35 MW Solar, unchanged from the 2011 plan
Yet there’s very little in the document about new solar power production, and nothing about wind. Pages 59 and 60 have this afterthought:
FPL also sought and received approval from the FPSC in 2008 to add 110 MW through three new FPL-owned solar facilities: one solar thermal facility and two photovoltaic (PV) facilities. One 25 MW PV facility began commercial operation in 2009. The remaining two solar facilities, a 10 MW PV facility and a 75 MW solar thermal steam generating facility, began commercial operation in 2010. The addition of these renewable energy facilities was made possible due to enabling legislation from the Florida Legislature in 2008. FPL remains strongly supportive of federal and/or state legislation that enables electric utilities to add renewable energy resources and authorize the utilities to recover appropriate costs for these resources. FPL is planning to introduce two new PV-based solar programs in 2014. These are discussed further in section III.F.4 of this chapter.
Well, what does III.F.4 say about that?
As part of its 2009 DSM Goals decision, the FPSC imposed a requirement for Florida’s investor-owned utilities to spend up to a set, not-to-exceed amount of money annually to facilitate demand side solar water heater and PV applications. FPL’s not-to-exceed amount of money for these applications is approximately $15.5 million per year through 2014. In regard to this direction, FPL received approval from the FPSC in 2011 to initiate a solar pilot portfolio that consists of three PV-based programs and three solar water heating-based programs, plus Conservation Research and Development. These programs are currently projected to be offered through 2014. FPL’s analyses of the results to-date from these programs shows that none of these programs are projected to be cost-effective using any of the three cost effectiveness screening tests used by the State of Florida. The fate of these solar programs, including their potential replacement with new solar initiatives, will be determined later in 2014 as part of the FPSC’s 2014 DSM Goals docket.
FL PSC made FPL look at solar, but FPL managed to find it not cost effective.
Meanwhile, a study from Stanford found all of Florida could be powered by 77.9% sun, 20% wind, 1% wave, 1% tide, and 0.1% hydro, with zero nuclear, coal, oil, or gas.
Why doesn’t FPL get on with sun and wind? Because they’re stuck in the century-old mindset of “capacity” and “baseload” power generation. As former FERC Chair Jon Wellinghoff said back in 2012, baseload is outdated:
“People talk about, ‘Oh, we need baseload.’ It’s like people saying we need more computing power, we need mainframes. We don’t need mainframes, we have distributed computing.”
“And, in fact, most plants running all the time in your system are an impediment because they’re very inflexible. You can’t ramp up and ramp down a nuclear plant. And if you have instead the ability to ramp up and ramp down loads in ways that can shape the entire system, then the old concept of baseload becomes an anachronism.”
“We are going to have to go to a smart grid to get to this point I’m talking about. But if we don’t go to that digital grid, we’re not going to be able to move these renewables, anyway. So it’s all going to be an integral part of operating that grid efficiently.”
In 2013 he got even more specific, saying:
“Solar is growing so fast it is going to overtake everything.”
“…at its present growth rate, solar will overtake wind in about ten years. It is going to be the dominant player. Everybody’s roof is out there.”
The last graph above is my projection using FERC’s own figures, which I made before I saw Wellinghoff’s projection. It matches: solar will win within a decade.
If FPL won’t do solar, others will. That’s why Wall Street is talking about the “death spiral” of utilities that won’t do solar power.
No useless fracked methane pipeline to help FPL deny the solar future. Let the sun rise on the Sunshine State.
-jsq
Short Link:
9 thoughts on “FPL’s own projections don’t support need for a new pipeline”