Three weeks after the date on the letter, I got this schedule notice from FERC, saying they plan to issue the final Environmental Impact Statement 18 December 2015, and they plan to rubberstamp the permit 17 March 2016, for Sabal Trail, Transco, and Florida Southeast Connection. So the opposition has made FERC slip the schedule a month.
This letter does mention a move for the Albany Compressor Station, but it looks to me like it’s referring to the previous site relocation.
-jsq
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSIONCP14-554-000
CP15-16-000
CP15-17-000Florida Southeast Connection, LLC
Transcontinental Gas Pipe Line Company, LLC
Sabal Trail Transmission, LLCNOTICE OF REVISED SCHEDULE FOR ENVIRONMENTAL REVIEW OF THE
SOUTHEAST MARKET PIPELINES PROJECT(November 19, 2015) Continue reading SMP Schedule