FERC rubberstamped FEIS for Sabal Trail today 2015-12-18

Just before Christmas, when the fewest people will be paying attention, Damages FERC just issued for Sabal Trail, FSC, and Transco Hillabee the Final Environmental Impact Statement (FEIS), aiming at March to rubberstamp a permit. You can still ecomment to FERC, or to the U.S. Army Corps of Engineers or to GA-EPD or ask your local, state, and federal elected and appointed officials to oppose this unnecessary, destructive, and hazardous boondoggle.

Curious how EPA changed its tune just before the FEIS.

Accession Number: 20151218-4001, “Final Environmental Impact Statement Volume I re the Southeast Market Pipelines Project under CP14-554 et al. Dated December”, with an announcement, Continue reading FERC rubberstamped FEIS for Sabal Trail today 2015-12-18

SMP Schedule

Three weeks after the date on the letter, I got this schedule notice from FERC, Letter saying they plan to issue the final Environmental Impact Statement 18 December 2015, and they plan to rubberstamp the permit 17 March 2016, for Sabal Trail, Transco, and Florida Southeast Connection. So the opposition has made FERC slip the schedule a month.

This letter does mention a move for the Albany Compressor Station, but it looks to me like it’s referring to the previous site relocation.

-jsq

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

CP14-554-000
CP15-16-000
CP15-17-000

Florida Southeast Connection, LLC
Transcontinental Gas Pipe Line Company, LLC
Sabal Trail Transmission, LLC

NOTICE OF REVISED SCHEDULE FOR ENVIRONMENTAL REVIEW OF THE
SOUTHEAST MARKET PIPELINES PROJECT

(November 19, 2015) Continue reading SMP Schedule