Tag Archives: National Environmental Policy Act

Construction of Sabal Trail pipeline is not inevitable –L. Elliott Jones

Especially preventable after Sabal Trail’s river easements went down in flames in a historic vote by the Georgia House last week. -jsq

L. Elliott Jones, Albany Herald, 28 March 2016, L. ELLIOTT JONES: Construction of Sabal Trail pipeline is not inevitable
GUEST COLUMNIST: Efforts are still under way to prevent the construction of the gas pipeline
,

Carlton Fletcher’s story, “Dougherty County leaders OK inevitable agreement on pipeline” on March 21, presented only one part of the current story on the Sabal Trail pipeline. There are two schools of thought on the Sabal Trail pipeline: those who believe construction of the pipeline is inevitable, and those who believe the pipeline can and should be prevented, and are working hard to do so. No one, in either group, believes it is needed in Georgia.

Continue reading Construction of Sabal Trail pipeline is not inevitable –L. Elliott Jones

Sabal Trail Notice of EIS Intent and Route Alternatives

A FERC comment period ending 15 November 2014 seems to mean Sabal Trail will miss its 31 October formal filing date. 300x391 Withlacoochee River Crossing Route Alternative, Hamilton and Suwannee Counties, Florida (bare), in Sabal Trail Notice of EIS Intent, by John S. Quarterman, for SpectraBusters.org, 15 October 2014 No relief suggested for crossing the Withlacoochee River at the border of Brooks and Lowndes Counties, Georgia (or inside Lowndes County next to Valdosta, according to several of the previous alternatives). And every proposed path still crosses the Suwannee River into Suwannee County.

Maybe that’s because the Dougherty County Commission and the Albany City Council actually stood up for their citizens, as did Gilchrist County (see Wacassassa Flats Alternative), while the Suwannee County Commission swallowed Sabal Trail disinformation and the Lowndes County Commission and the Valdosta City Council did little (except one letter from the Chairman) or nothing (except one letter from one Council member).

300x131 Sasser Route Alternative, Albany Compressor station Alternatives, Terrell, Lee, and Dougherty Counties. Georgia (bottom), in Sabal Trail Notice of EIS Intent, by John S. Quarterman, for SpectraBusters.org, 15 October 2014 There’s still time for Dougherty, Lowndes, and all the other counties and cities to pass ordinances, and to lobby state and federal agencies and elected and appointed officials. Oh, and there’s an election going on.

Also no mention of Sabal Trail’s Jasper, Florida Open House, 5-7:30 Tuesday 21 October 2014, but STT’s newspaper notice said the public is invited, so y’all come!

Filed with FERC today, 15 October 2014, Supplemental Notice of Intent to Prepare an Environment Impact Statement for the Planned Southeast Market Pipeline Project and Request for Comments on Environmental Issues etc. re Sabal Trail Transmission, LLC under PF14-1.

-jsq

Docket No. PF14-1-000

Continue reading Sabal Trail Notice of EIS Intent and Route Alternatives

FERC has to consider cumulative pipeline effects

Would this U.S. Court of Appeals ruling mean FERC needs to consider the cumulative effects of the proposed Sabal Trail pipeline on the same properties as the existing SONAT pipeline? And what about those LNG export authorizations FERC has repeatedly claimed it knows nothing about? And how can FERC justify that project at all, given that solar power is faster, cheaper, and far less environmentally damaging?

Katie Colaneri wrote for NPR 6 June 2014, Court rules federal regulators must consider cumulative impacts of pipeline project,

Regulators violated federal law by not considering the cumulative environmental impacts of multiple upgrades to a natural gas pipeline that runs from Pennsylvania to New Jersey, a federal appeals court said on Friday.

Three environmental groups argued the Federal Energy Regulatory Commission (FERC) should not have been allowed to conduct an environmental review for one expansion project on the Tennessee Gas Pipeline without considering three other proposed upgrades on the same line.

The U.S. Court of Appeals agreed.

The judges ruled that FERC failed “to include any meaningful analysis of the cumulative impacts of the upgrade projects.” The judges also found Continue reading FERC has to consider cumulative pipeline effects